Inground Vinyl Liner Pool Construction
Before any construction starts we will have a site meeting to finalize the size, shape, and location of the pool.
The first step of construction is excavation, in the event that we hit a high water table or ledge we will notify you of any changes or extra expenses.
After excavation is done we will set the aluminum walls and the stairs. We will make sure everything is perfectly level with a laser level.
Once the walls and stairs are set we will pour a concrete collar around the outside of the pool, pour the bottom of the deep end, and pour the bottom of the shallow end. After we are done pouring concrete the electrician is good to come and do any electrical work that is needed.
At this stage we will do all of our plumbing, and set up all of the pool equipment. (Pump, Filter, Salt System, Heater)
After the plumbing and electrical is complete we will backfill and rough grade for the patio.
Once we have finished backfill and grading, we will vermiculite the bottom of the pool. At this stage we will need access to a hose and power.
Next is Install the vinyl liner. We will put down foam padding in the shallow end, and install the liner with a special vacuum to insure a perfect fit without any wrinkles.
The final step in construction is have the water truck fill the pool to halfway up the skimmer.
Once construction is complete we will answer any questions you might have, drop off any accessories outlined in the contract, and go over basic pool care.
In-ground Pools - Concrete Patios - Hot Tubs